3.3.1.6 Project Plan Hours VS Actural Hours report
1. Introduction
Count and compare planned hours and actual hours of the project to calculate the project progress.
Example of Project Plan Hours VS Actural Hours report:
Support by Project or Filter dimension
2. Permission required
Sort by Project
All users can use this report, and only the following users can edit the plan and actual data of the corresponding project:
Project Leader
Users with Extend [Administer Projects] permissions
Sort by Filter
All users can use this report for the filters they can view, and only the following users can edit the corresponding filter's plan start/end date, planned hours, and actual start/end dates:
Users with edit permission on the filter
Jira-administrators user group
3. Function
3.1 Description
3.1.1 Project query
As indicated at mark 1, support sorting by 'Project' or 'Filter', and select projects or filters through the selection box.
3.1.2 Project actual
As indicated at mark 2, "project actual" shows the actual hours that has been taken.
Start date: if start date is not configured manually , the create date of the first issue in a project will be set as the start date.
End date: if end date is not configured manually, all the actual hours after "Start date" will be cumulatively counted.
Hours: all logged hours in a project will be automatically caculated based on its started date and end date.
3.1.3 Project plan
As indicated at mark 3, "project plan" shows the estimation of project manager on project's start date, end date and hours.
Start date: an estimated day when a project starts
End date: an estimated day when a project is done
Hours: total hours a project will take.
3.1.4 Project Progress
As indicated at mark 4, the number helps project managers understand project's progress and respond accordingly. This number is the ratio of "project actual hours" to "project plan hours".
Green: ratio <= 80%
Yellow: 80% < ratio <= 100%
Red: ratio > 100%
3.1.5 Actions
As demonstrated at mark 5, two actions are availabe: "edit" and "view history"
edit: start date, end date and hours are editable. Please note:
When sorting by Project, this button is displayed only if the current logged on user is one of the following two types of users:
Project Leader
Users with Extend [Administer Projects] permissions
When sorting by Filter, this button is displayed only if the current logged on user is one of the following two types of users:
Users with edit permission on the filter
Jira-administrators user group
view history: click and a modification history sreen as below will show up
View history:Click to view the modified history, as shown in the figure below
3.2 Share report
For more details, please refer to3.3.4 Share report
Note: The sharing of Project Plan Hours VS Actural Hours report does not distinguish between viewing and editing, as the editing permissions for the report depend on whether the current logged on user is one of the following two types of users:
Project Leader
Users with Extend [Administer Projects] permissions
3.3 Send report
For more details, please refer to3.3.5 Send and Scheduled send report
Note: Project Plan Hours VS Actural Hours report does not support scheduled sending.
3.4 Export report
For more details, please refer to3.3.6 Export report
Export example: