3.3.1.5 Estimated time report
1. Introduction
Estimated time report can display the time data of each issue in detail, including original estimated time, the remaining estimated time, and the actual spent time, and compare them, so that the project manager can effectively grasp the progress of each work.
Example of Estimated time report:
2. Permission required
The following users have the permission to create the estimated time report. Users without permission will hide this report.
Jira project leader
Users with the project role of TimeWise Project View
Users with the project role of TimeWise Project Approver
Users with extended [Administer Projects] permissions
3. Function
3.1 Query dimension
support querying issues by project or filter:
Click "More" to query by Epic, Version, Component and Sprint.
3.2 Group by
The default structure is Project>>Epic>>Issue, and you can also choose to combine versions, components, and Sprints.
Note: In the selected list, projects can only be listed first and issues can only be listed last.
3.3 Customize the columns to be displayed
Among them, “Time in Difference” and “progress” are columns extended by TimeWise, and the calculation rules are as follows:
Time in Difference = Original Estimated Time - Time Spent - Remaining Estimated Time
Progress = Time Spent / (Time Spent + Remaining Estimated Time) *100%
3.4 Share report
For more details, please refer tohttps://dragonsoft.atlassian.net/wiki/spaces/GXDOCSPACE/pages/2153578728
3.5 Send report
For more details, please refer tohttps://dragonsoft.atlassian.net/wiki/spaces/GXDOCSPACE/pages/2153775224
Note: The estimated time report does not support scheduled sending.
3.6 Export report
For more details, please refer tohttps://dragonsoft.atlassian.net/wiki/spaces/GXDOCSPACE/pages/2153578755
Export example: