1.2 Calendar Scheme
1. Introduction
For special dates that do not meet the standard working days, you can define whether they are working days in the calendar scheme.
2. Permission Required
To be able to configure, you must be a Jira administrator. This menu bar will not display to users without required permission.
3. Configuration
Go to TimeWise > click Configuration > Calendar Scheme Configuration.
You can see all configured schemes on page as below.
3.1 Add a Scheme
Click Add to create a new calendar scheme. Select Set a calendar scheme and click Confirm, then you can see a page of Scheme settings.
3.2 Edit, Delete Scheme
Click Name and Description and edit directly
Click copy or delete option. These two actions will effect on the whole scheme including all calendars in this schemes
3.3 View
Click view icon, you can see all configured calendars in this schemes as below.
3.4 Calendar Scheme Configuration
Click setting icon, a pop-out window will provide you edit and delete options for configuring calendars in this scheme.
Click Add, insert a new item into the scheme.
To bulk import calendars, click Import. So far it can support import as CSV, ICS or URL of ICS. Follow the instructions on the page.
Choose a file or type in URL of availabe iCalendar file,click Next to enter to the Confirm page.
If no error occurs, click Import to enter to the Success page.