2.2.2 Project Workday Scheme (No longer supported by versions 4.2.0 and later)
Go to Project > TimeWise Setting
>1.View Project Workday Scheme
If no scheme has been configured yet, a default scheme will be applied to global.
2.Switch to Another Scheme
Click
, a pop-out window will allow you to choose another scheme.A workday scheme can be applied to one single project as well. If there is any scheme attached to a project, this project will use this scheme rather than a global one.