Example of Project Plan Hours VS Actural Hours report:
...
Support by Project or Filter dimension
...
2. Permission required
Sort by Project
All users can use this report, and only the following users can edit the plan and actual data of the corresponding project:
Project Leader
Users with Extend [Administer Projects] permissions
Sort by Filter
All users can use this report for the filters they can view, and only the following users can edit the corresponding filter's plan start/end date, planned hours, and actual start/end dates:
Users with edit permission on the filter
Jira-administrators user group
3. Function
3.1 Description
...
3.1.1 Project query
Select projects in dropdown menu from the highlighted "Project" selection at mark 1. As indicated at mark 1, support sorting by 'Project' or 'Filter', and select projects or filters through the selection box.
3.1.2 Project actual
As indicated at mark 2, "project actual" shows the actual hours that has been taken.
...
edit: start date, end date and hours are editable. Please note:
When sorting by Project, this button is displayed only if the current logged on user is one of the following two types of users:
Project Leader
Users with Extend [Administer Projects] permissions
When sorting by Filter, this button is displayed only if the current logged on user is one of the following two types of users:
Users with edit permission on the filter
Jira-administrators user group
view history: click and a modification history sreen as below will show up
...
For more details, please refer to/wiki/spaces/GXDOCSPACE/pages/2153578755 3.3.6 Export report
Export example:
...