Work logs/Plans are display in the issue view like so:
From left to right, the type (work plan/log), work plan/log notesremark, user Author (visible to project managers only), date, scheduled/recorded work time, edit and delete functions .
...
If the current issue is in a project that has auditing enabled, auditing status and information is displayed as follows:
Project Manager:
|
Note:
For periodic work plans, the "Date" column above is the plan start date, and below is the plan end date; the "Scheduled Work Time" column above is the planned total work hours, and the lower brackets are the daily planned work hours.
View Details, Edit and Delete functions will only be displayed when the mouse is over the work plan.
...
4. Editing work plans/logs
...
If the audit function is not enabled for the current project: Users with the TimeWise Project Manager permission can edit work plans created by regular project members, but and can edit others' t edit work logs of regular project membersdepends on the permission scheme.
If the audit function is enabled for the current project: Work plans and logs in the Pending or Audited status cannot be editied.
...
If the audit function is not enabled for the current project: Users with the TimeWise Project Manager permission can delete work plans created by regular project members, but and can delete others' t delete work logs of regular project membersdepends on the permission scheme.
If the audit function is enabled for the current project: Work plans and logs in the Pending or Audited status cannot be deleted.
...